Total gas storage and deliverability capacity of the AECO Hub™:

Working Gas Capacity 154.00 BCF
Peak Withdrawal Rate 3.05 BCF per day
Peak Injection Rate 2.75 BCF per day

The two facilities contribute to the total capability in approximate proportion to their working gas capacities:

Suffield 83.5 BCF
Countess 70.5 BCF

Below are further facts on the total facilities that comprise the AECO Hub™:

Number of reservoirs 7
Number of compression plants 6
Number of compressors 15 (gas powered)
7 (electric powered)
22 (total)
Total compression horsepower 70,500 bhp
Storage wells 89